NERC Compliance
PRC-027-1
One Minute Summary - NERC PRC-027-1
Coordination of Protection Systems for Performance During Faults
Purpose:
Maintain the coordination of protection systems
Detect and isolate faults
Relay operates in the intended sequence during faults
Benefits
Isolate Faulted Equipment
Reduce BES Instability and Cascading Risks
Keep Remainder of BES Operational
Protect Equipment from Damage
Minimize Removal of BES Elements
Prepare for Next Contingency
Functional Eentity
Transmission Owner
Provide the Fault current data upon request by the Distribution Provider or Generator Owner
Generator Owner
Ensure that generation Facilities are not unnecessarily disconnected
Determine whether a change in Fault current from the baseline
Distribution Provider
Provide an electrical interconnection and path to the BES
Coordinated with other Protection Systems
Determine whether a change in Fault current from the baseline
R1 Establish a process to develop new and revised protection system
Ensure accurate settings
Internal and external checks to minimize the possibility of errors
There is no a one-size-fits-all criterion for “Protection System coordination”, different entities might have varying technical criteria
Line differential is not required
Backup protection systems
Use current or apparent impedance with time delay
Must be coordinated with other protection systems
Does not trip unnecessarily for faults outside of the differential zone.
1.1 Review and update of short-circuit model data
Impedances and Fault currents for
Line
Transformer
Generator
System network as the actual system
Information from
Interconnected Transmission Owner
Generator Owner
Distribution Provider
1.2 Review of the developed protection system settings
Peer reviews
Automated checking programs
Review procedures
1.3. Coordination with electrically join facilities (only apply to electrically join facilities)
1.3.1. Share the proposed protection system settings
Other entities can review the settings and determine issues
1.3.2. Respond to any owner(s) that provided its proposed Protection System settings:
Identifying coordination issues
OR confirming no issues were identified
1.3.3. Verify coordination issues are addressed
Exclusion for Individual Dispersed Generation Resources in Requirement R3, R3.1
1.3.4. Communicate about revised Protection System settings:
Unforeseen circumstances during implementation or commissioning,
Misoperation investigations
Maintenance activities
Emergency replacements required due to Protection System component failure.
R2 Timeline to perform a Protection System Coordination Study
Option 1 (Time-based):
Perform a Protection System Coordination Study every six years
Option 2 (Fault current-based):
Compare present Fault current values to an established baseline and perform a study if there is a 15 percent or greater deviation (for either three-phase or phase-to-ground faults), within a six-calendar-year interval.
Option 3: Use a combination of Option 1 and Option 2
Protection System Coordination includes:
21 – Distance if:
• Infeed is used in determining reach for phase 21 and ground distance 21
• zero-sequence mutual coupling is used in determining reach (ground distance).
50 – Instantaneous overcurrent
51 – AC inverse time overcurrent
67 – AC directional overcurrent if used in a non-communication-aided protection scheme
Establish and maintain an Fault current baseline
Initial Establishment of Baseline
Established by the effective date of the Reliability Standard.
Provisions for Missing Initial Baseline:
Establish the baseline by performing a Protection System Coordination Study.
Update the Baseline:
Updated each time a Protection System Coordination Study is performed.
Baseline for BES Generating Resources
Fault current baseline can be established at:
At the generator
At the generator step-up (GSU) transformers
At the common point of connection at 100 kV or above.
Dispersed Power Producing Resources:
Fault current baseline can be established at
at the BES aggregation point, provided the total capacity is greater than 75 MVA.
R3 Utilize established process in requirement R1
Consistent approach
Decreases the possibility of errors
Increases the likelihood of maintaining a coordinated Protection System