NERC Compliance 

PRC-028-1

One Minute Summary - NERC PRC-028-1 

Disturbance Monitoring and Reporting Requirements for 

Inverter Based Resources 

Reference from Technical Rationale for Reliability Standard PRC-028-1 

Background:

The recent disturbance reports as below highlighted the need for disturbance monitoring for inverter-based resources (IBRs). 

Purpose:

Install disturbance monitoring equipment (DME) at wind and solar PV resources assisted with event analysis, performance monitoring, and IBR generating facility model validation.

Difference from PRC-002 Disturbance Monitoring and Reporting Requirements :

PRC-002 Purpose: 

Capture data to understand large-scale disturbances on the Bulk Electric System (BES).

PRC-002 Issues:

Solution:

Responsibilities:

The following entities ensure adequate data availability for applicable Elements at IBR generating facilities:

Mandated data: 

Figure 1, reference from Technical Rationale for Reliability Standard PRC-028-1 

Requirement R1:

Aim: Capture SER (Sequence of Events Recording) data from circuit breakers and IBR (inverter-based resources) units within the IBR generating facility.

Specifics: At least one IBR unit connected to the last 10% of each collector feeder length must have data as specified in R1, Part 1.2.1 through 1.2.6.

1.2.1. All fault codes. 

1.2.2. All fault alarms. 

1.2.3. Change of operating mode. 

1.2.4. High and low voltage ride-through. 

1.2.5. High and low frequency ride-through. 

1.2.6. Control system command values, reference values, and feedback signals. 

Importance of Data to provides a detailed sequence of events timeline of the IBR generating facility's response during a power system disturbance.:

Analysis Process:

Why Record One IBR Unit in the Last 10% of the Collector Feeder Length:


Requirement R2:

Aim: Capture sufficient Fault Recording (FR) data for Elements at each IBR (Inverter-Based Resources) generating facility to analyze its response to system disturbances.

Plant Level FR Measurements:

IBR Units' Response to Disturbances:

Dynamic Reactive Device:

Recording of Electrical Quantities:

Current Recordings:

Voltage Recordings:

Requirement R3:

Aim: Time-stamped pre- and post-trigger Fault Recording (FR) data assists in analyzing power system operations and determining if operations were as intended.

Odessa Disturbance Report Recommendations:

Importance of Pre- and Post-Trigger Data:

----------------------------------------------------------------------------------------------------------------------------------

Each Transmission Owner and Generator Owner shall have FR data as specified in Requirement R2 that meets the following:

3.1. High-side of the main power transformer FR data 

3.1.1. A single record or multiple records that include a pre-trigger record length of at least two cycles and a total record length of at least 2.0 

seconds for the same trigger point. 

3.1.2. A minimum recording rate of 128 samples per cycle. 

3.1.3. Trigger settings for at least the following: 

3.1.3.1. Neutral (residual) overcurrent. 

3.1.3.2. AC phase overvoltage and undervoltage. 

3.2. IBR unit level data 

3.2.1. A single record or multiple records that include a pre-trigger record length of at least two cycles and a total record length of at least 2 

seconds for the same trigger point.  

3.2.2. A minimum recording rate of 128 samples per cycle. 

3.2.3. Trigger settings for at least the following: 

3.2.3.1. AC Phase overvoltage and undervoltage. 

3.2.3.2. DC overvoltage, DC overcurrent, and DC reverse current. 

3.2.3.3. Overfrequency and underfrequency. 

3.3. Dynamic reactive device FR data 

3.3.1. A single record or multiple records that include a pre-trigger record length of at least two cycles and a total record length of at least 2.0 

seconds for the same trigger point. 

3.3.2. A minimum recording rate of 128 samples per cycle. 

3.3.3. Trigger settings for at least the following: 

3.3.3.1. Neutral (residual) overcurrent. 

3.3.3.2. AC phase overvoltage and undervoltage. 

Requirement R4:

Aim:  Each Generator Owner and Transmission Owner shall have continuous dynamic Disturbance recording (DDR) data and storage to determine the following electrical quantities for each main power transformer(s) it owns.

Importance of DDR Data:

Nature of DDR Data:

Usage of DDR:

Data Requirements for PRC-028-1:

Significance in Disturbance Analysis:

Requirement R4, Part 4.1:

Requirement R5:

Aim:  DDR data should have the electrical quantities identified below:

Input Sampling Rate:

Output Recording Rate:

Requirement R6:

Aim:  Time synchronize all SER, FR, and DDR data to meet the following: 

Importance of Time Synchronization:

Accuracy of Time Synchronization:

Monitoring Devices Internal Clocks:

IBRs and Time Synchronization:

Requirement R7:

Aim: Data Retrievability

Data Provision Requirement:

Standardized Formatting and Naming:

SER Data - Requirement R7, Part 7.3:

FR and DDR Data - Requirement R7, Part 7.4:

Naming Convention - Requirement R7, Part 7.5:

Requirement R8:

Aim: within 90 calendar days of the discovery of a failure of the recording capability for the SER, FR, or DDR data

Restoration Requirement:

Rationale for 90-Day Period:

Exceptions and Corrective Action:

Definition of Failure: